Certified Maintenance & Reliability Professional (CMRP) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Certified Maintenance and Reliability Professional Exam. Utilize flashcards and multiple choice questions, each with explanations and tips. Ensure exam success!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which risk category assesses the adequacy of time allocated for tasks?

  1. Cost Risk

  2. Performance Risk

  3. Schedule Risk

  4. Technology Risk

The correct answer is: Schedule Risk

The assessment of the adequacy of time allocated for tasks falls under Schedule Risk. This category specifically focuses on the potential for delays within a project due to time management issues. Proper scheduling is crucial for maintaining the timeline of a project, and any inadequacies in time allocation can lead to missed deadlines, impacting project completion and overall performance. Schedule Risk evaluates how likely it is that time constraints will affect the execution of tasks, ensuring that sufficient time is allocated to complete each stage of a project effectively. In contrast, Cost Risk examines financial implications and budget overruns, Performance Risk evaluates the effectiveness and outcomes of the tasks, and Technology Risk considers the challenges associated with the technologies being used. Each of these categories has its own focus, setting Schedule Risk apart as the category specifically concerned with time management and allocation within project frameworks.